Current status at a glance
The table distinguishes a completed public milestone from a target or reported position. “Not publicly verified” means Civic Ledger did not locate a current primary record confirming completion; it is not proof that no work has occurred.
| Milestone | Public position at 25 September 2026 | Evidence status |
|---|---|---|
| Industrial gas supply | Supply to third-party users is expected to tighten from 2028 as Mozambique’s Pande–Temane output declines. | Parliament describes the expected gas cliff; exact customer-by-customer exposure is not publicly listed. |
| TNPA–ZET agreement | A 25-year terminal-operator agreement was signed in February 2025 for the Richards Bay South Dunes LNG project. | Official government announcement. |
| Gas-to-power procurement | Bid Window 1 seeks 2,000 MW. The submission deadline was 29 May 2026; four bids totalling about 2,800 MW were reported at the September 2026 webinar. | Programme scope and deadline are in official records; bid count/capacity is attributed to webinar reporting. |
| ZET engineering | A front-end engineering design decision was reported as planned for November 2026. | Project representative’s timetable, reported by Mining Weekly; future milestone. |
| ZET investment decision | Target reported for early or mid-2028. | Reported target; financial close/investment decision not publicly verified here. |
| ZET Phase 1 operation | Commercial operation targeted for 2030 after roughly two years of construction. | Reported target; no completed terminal or commercial gas delivery verified. |
| Schedule assessment | High risk, with little or no contingency against the 2030 deadline. | Civic Ledger assessment based on the reported 2028 investment and two-year build sequence. |
What is South Africa’s gas cliff?
The “gas cliff” describes the expected decline in gas supplied from Mozambique’s Pande and Temane fields through the ROMPCO pipeline. Parliament’s electricity committee described the expected decline by 2028 as a risk to South Africa’s energy supply and industrial base. The term does not mean South Africa has already run out of gas or that every household is about to lose supply.
Industrial users are the immediate focus of the warnings. Recent industry and university commentary has referred to more than 300 industrial buyers in Gauteng and Mpumalanga. That number is attributed to the webinar coverage and should not be read as a published, audited register of affected customers.
What is the Zululand Energy Terminal?
ZET is the proposed LNG import terminal at the Port of Richards Bay. LNG—liquefied natural gas—is natural gas cooled into liquid form for transport by ship. At an import terminal it is stored and converted back into gas, which can then enter connected pipelines.
The project’s proponents are Vopak Terminal Durban and Transnet Pipelines. TNPA’s official announcement says the operator agreement covers the design, development, financing, construction, operation and maintenance of the terminal for a 25-year concession period. Transnet describes the Lilly Pipeline as carrying methane-rich gas and lists Richards Bay and Empangeni among delivery points. That establishes a potential infrastructure connection, not proof that LNG can already flow through it.
Gas-to-power procurement: the bankability link
The Department of Electricity and Energy’s Gas IPP Procurement Programme Bid Window 1 seeks 2,000 MW of new gas-fired generation capacity. The official programme page describes a long-term power-purchase arrangement and identifies Eskom as the intended buyer. The bid deadline was extended to 29 May 2026 and remained unchanged in the department’s 15 April notice.
There is a source-control issue worth noting: the IPP-Gas programme overview still displays its original 30 August 2024 bid-submission date. A later Department of Electricity and Energy notice dated 15 April 2026 says the bid-registration deadline was extended and confirms that the bid-submission date of 29 May 2026 remained unchanged. For the current deadline, the later dated notice supersedes the old overview timetable.
The Department’s programme page reviewed for this tracker listed procurement notices through 17 April 2026. In coverage of the 22 September webinar, preferred bidders were still awaited and four bids offering about 2,800 MW were reported. The bid count and capacity are attributed to that reporting, not presented as a figure in the official programme notice.
The September webinar coverage reported that four bids offered approximately 2,800 MW and that preferred bidders were still awaited. It also reported that ZET regarded the preferred-bidder announcement as an initial trigger for its engineering work. This is an important reported dependency: power procurement may help establish demand and support financing, but it is not itself a terminal construction contract, LNG supply agreement or guarantee of gas availability.
Why the 2030 timetable is exposed
The latest reported sequence is tight: a front-end engineering decision planned for November 2026; environmental assessment and engineering, procurement and construction planning thereafter; a final investment decision in early or mid-2028; and roughly two years of Phase 1 construction. The stated goal is commercial operation in 2030.
This leaves little visible contingency for a project involving marine works, LNG storage and regasification equipment, environmental authorisations, financing, LNG procurement, pipeline connections and customer commitments. The project timetable may still be achievable; Civic Ledger’s finding is that the public sequence does not show meaningful schedule slack. Each milestone must be verified as it occurs.
Accountability and evidence to watch
Civic Ledger will update this record when an official notice, signed agreement, regulatory record or attributable project statement changes the position. The milestones below are the minimum evidence needed to test whether the 2030 target remains credible.
| Decision or deliverable | Lead institution or party | Evidence Civic Ledger will look for |
|---|---|---|
| Gas IPP preferred bidders and project agreements | Department of Electricity and Energy / IPP Office; Eskom as buyer | Official preferred-bidder notice, project list, power-purchase agreement milestones and conditions. |
| ZET engineering and environmental process | ZET; relevant port and environmental authorities | Published engineering decision, EIA decision/appeal status, permits and dated construction scope. |
| Final investment decision and financing | ZET shareholders and lenders | Formal investment decision, financing commitments and conditions precedent. |
| LNG supply and customer commitments | ZET, LNG suppliers, industrial customers and power projects | Executed supply/offtake contracts, volumes, pricing basis, delivery windows and conditions. |
| Lilly Pipeline integration and upgrades | Transnet Pipelines | Approved scope, capacity, licences, funding, construction milestones and commissioning evidence. |
| Commercial operation and first gas | ZET, TNPA, Transnet Pipelines and customers | Commissioning certificate, operating authorisations, first LNG cargo/regasification and confirmed delivery. |
What the signed agreement does—and does not—prove
The 25-year terminal-operator agreement is a material project milestone. It gives ZET the right to develop and operate the planned terminal under the concession framework described by TNPA. It does not, by itself, prove a final investment decision, committed project finance, completed environmental approvals, signed LNG purchase contracts, a completed pipeline, or a date on which customers will receive gas.
Similarly, an announced gas-to-power procurement target and bids received do not prove that generating projects have reached financial close or that the LNG terminal has a bankable customer. Civic Ledger will mark those as separate stages.
Sources, method and update policy
Primary records are preferred for agreements, procurement scope, legal status and infrastructure facts. Statements about future dates are labelled as targets. Claims from a webinar reported by a news outlet are labelled as secondary reporting. The “high schedule risk” label is Civic Ledger’s own assessment, based on the dated sequence described above.
This tracker was first published on 25 September 2026. It is not a substitute for formal project, procurement or regulatory notices. Last verified: 25 September 2026. No official source reviewed for this page confirms that ZET has reached financial close or started construction. If an agency, project company or affected party has a newer document, send it to hello@civicledger.co.za; the source and the resulting change will be recorded.
Frequently asked questions
Is South Africa currently out of gas?
No. The “gas cliff” refers to an expected decline in existing pipeline supply, with industrial supply pressure expected from 2028. The warning is about a future supply gap, not a claim that the country has already run out.
When is the South African gas shortage expected?
The supply decline is expected to begin around 2028 as Mozambique’s Pande and Temane fields decline. Sasol’s proposed methane-rich gas bridge and LNG import infrastructure are intended to manage the transition, but their timing and delivery must be tracked separately.
What is the Zululand Energy Terminal?
It is a proposed LNG import terminal at the Port of Richards Bay, developed by a partnership between Vopak Terminal Durban and Transnet Pipelines under a 25-year terminal-operator agreement with TNPA.
When will Richards Bay’s LNG terminal open?
The latest timetable located by Civic Ledger is a 2030 Phase 1 commercial-operation target reported after a September 2026 webinar. It is a target, not a verified opening date.
Has ZET started construction or reached financial close?
Civic Ledger did not locate a current primary record confirming financial close or construction commencement by 25 September 2026. This means not publicly verified in the sources reviewed, not necessarily that no preparatory work exists.
Why does gas-to-power procurement matter to the terminal?
The gas IPP programme may create a large long-term gas customer and help make LNG infrastructure financeable. Procurement and terminal construction are separate processes; one does not automatically guarantee the other.
What is Civic Ledger’s assessment of the deadline?
High schedule risk. The reported timetable places the investment decision in early or mid-2028 and Phase 1 construction at roughly two years, against a 2030 operating target. That leaves little or no visible contingency.
What it means
The central accountability issue is not whether LNG has been proposed. It has. The question is whether demand commitments, procurement, approvals, financing, construction and pipeline connections will reach completion before existing supply declines. Civic Ledger will retain dated milestones and distinguish official decisions from forecasts and industry claims.
Correction history
No material correction is recorded for this article as of 25 September 2026. Any correction will be listed on the corrections register.
Sources and reporting
Linked sources- Committee on Electricity calls for urgency in addressing South Africa’s gas cliff ↗
- Gas IPP Procurement Programme: Bid Window 1 overview ↗
- GASIPPPP Bid Window 1 Notice 7: bid registration extension; submission date remains 29 May 2026 ↗
- TNPA signs milestone agreements for Richards Bay South Dunes precinct ↗
- Zululand Energy Terminal: South Africa’s first LNG import terminal ↗
- Transnet transmission infrastructure: Lilly Pipeline capacity information ↗
- Gas Bill (B6-2026): Parliament bill record ↗
- South Africa urged to take action as 300 industrial buyers face gas cliff ↗
Source record
Sources and reporting
Linked sources- Committee on Electricity calls for urgency in addressing South Africa’s gas cliff ↗
- Gas IPP Procurement Programme: Bid Window 1 overview ↗
- GASIPPPP Bid Window 1 Notice 7: bid registration extension; submission date remains 29 May 2026 ↗
- TNPA signs milestone agreements for Richards Bay South Dunes precinct ↗
- Zululand Energy Terminal: South Africa’s first LNG import terminal ↗
- Transnet transmission infrastructure: Lilly Pipeline capacity information ↗
- Gas Bill (B6-2026): Parliament bill record ↗
- South Africa urged to take action as 300 industrial buyers face gas cliff ↗