N2 KwaMashu–uMdloti upgrade
Major N2 upgrade between KwaMashu and uMdloti. eThekwini reported the project at 96% completion on 22 September 2026, with completion expected by 2 November 2026.
The city’s Executive Committee briefing put the N2 project at 96% completion and listed 2 November 2026 as its expected completion date.
Tender records carry reference numbers, dates, institution, status and original-source links. Unreported values remain undisclosed.
Every amount is labelled as budgeted, estimated, committed, contracted or spent where the source supports that distinction. If the document does not state a value, the record says so.
Read the standards →Major N2 upgrade between KwaMashu and uMdloti. eThekwini reported the project at 96% completion on 22 September 2026, with completion expected by 2 November 2026.
N3 interchange upgrade. eThekwini reported 44.6% completion and an expected September 2028 completion date on 22 September 2026.
eThekwini reported rehabilitation of 13 inner-city roads during 2025/26 and more than R127m invested through the programme. The release did not provide a full contract-by-contract schedule.
Reconstruction of the flood-damaged Illovo Railway Bridge. eThekwini and PRASA said in April 2026 that they would fast-track the work; no value, construction start or completion date was stated in that release.
The municipality says 13 roads were rehabilitated during 2025/26, including routes through the Durban city centre. The statement describes programme investment, not a single contract award.
TNPA named preferred bidders for fresh-produce and agricultural dry-bulk terminals. The authority said negotiations on terminal-operator agreements were the next step.
A city statement on 31 August described progress on the private-sector development led by Fundamentum. It did not publish a full phase-by-phase delivery schedule.
The adopted 2026/27 MTREF places about R69bn in operating expenditure and R6.3bn in capital expenditure. The capital figure is the investment plan for the year, not a record of cash already spent.
The March draft set 2026/27 capital spending at R5.9bn; the adopted framework reports R6.3bn. The change is a budget revision, not evidence of spending already completed.
The draft budget described multi-year programme envelopes for wastewater, water-loss reduction, electricity, housing, transport and roads. Those envelopes are not individual tenders.
The municipality says 13 roads were rehabilitated during 2025/26, including routes through the Durban city centre. The statement describes programme investment, not a single contract award.
A council decisions record lists two regional wastewater works for PPP delivery at a reported R2.1bn and the Southern Aqueduct at about R1.1bn. Those programme figures do not, by themselves, prove that the full amounts have been contracted or spent.
Major N2 upgrade between KwaMashu and uMdloti. eThekwini reported the project at 96% completion on 22 September 2026, with completion expected by 2 November 2026.
N3 interchange upgrade. eThekwini reported 44.6% completion and an expected September 2028 completion date on 22 September 2026.
eThekwini reported rehabilitation of 13 inner-city roads during 2025/26 and more than R127m invested through the programme. The release did not provide a full contract-by-contract schedule.
Reconstruction of the flood-damaged Illovo Railway Bridge. eThekwini and PRASA said in April 2026 that they would fast-track the work; no value, construction start or completion date was stated in that release.