Project record
Corridor 3 is intended to connect Bridge City in KwaMashu with Pinetown and become the first operating GO!Durban corridor. A public-transport industry process agreement was signed on 30 October 2026, but operating contracts and system commissioning remain outstanding before the targeted December launch.
A missing value, contractor or date means no supported figure was present in the cited records reviewed for this page.
Timeline
Append-only status history- Under Construction · City update described a December 2026 service launch as on track.
- Agreement Signed · The City and bus and minibus-taxi industry representatives signed the C3 Process Agreement and unveiled a GO!Durban bus.
- Reported · The signing appeared on the municipal news page; operating contracts and testing remained outstanding.